Mistake & recovery · #102

Building a double-wall duct liner panel that shifts during assembly

3rd YearFabrication

Pin liner panels at regular intervals with mechanical fasteners per SMACNA specifications — typically every 6" at edges and 12" in the field. Adhesive alo…

Search Field RescueAsk ForemanOpen in mistake guide

Safer field move

Pin liner panels at regular intervals with mechanical fasteners per SMACNA specifications — typically every 6" at edges and 12" in the field. Adhesive alone is insufficient, especially in high-velocity systems.

Ask Foreman

Can you verify this before I keep going? I’m looking at: Building a double-wall duct liner panel that shifts during assembly. What’s the approved correction for this job?

Do not

Do not hide, force, cover, or “make it work” if this affects safety, access, airflow, rated assemblies, supports, equipment, or inspection. Stop and verify the approved correction.