Airside Controls · VAV Terminal Units

VAV with hot-water reheat

VAV terminal unit — Above ceiling

ConnectionAir + hydronic coil
SupportIndependent support

How to install it

  1. 1

    Hang level

  2. 2

    connect ducts

  3. 3

    connect insulated water piping with valves and drain/vent

  4. 4

    pressure-test

  5. 5

    wire controls

  6. 6

    commission.

Quality check

  • Coil accessible, valves reachable, no leaks

Stop and verify

Stop if coil piping blocks access