Commercial Split Systems · Refrigerant line coordination

Route line set

Equipment Installation — Split system

Task typeRefrigerant line coordination
Tools / equipmentLine supports, insulation, approved tools

How to install it

  1. 1

    Follow approved design and manufacturer limits

  2. 2

    support and protect lines

  3. 3

    maintain bend radius

  4. 4

    insulate suction line

  5. 5

    coordinate brazing/pressure test by qualified personnel.

Quality check

  • Lines supported
  • insulation continuous
  • no kinks

Stop and verify

Stop if sizing, length, elevation, or refrigerant procedure is unknown