Air-Handling Units · Final AHU installation check
Pre-start field verification
Equipment Installation — Complete unit
Task typeFinal AHU installation check
Tools / equipmentChecklist, camera
How to install it
- 1
Verify anchorage, section seals, filters, drains, doors, guards, duct supports, flex connectors, shipping restraints, and cleanliness
- 2
document deficiencies.
Quality check
- Unit ready for manufacturer/startup team
Stop and verify
Stop startup until critical installation defects are corrected